“Rule of Thumb” for bond pattern between courses: Construct the wall using the units as they come off each shipping pallet. Randomly utilize the various unit shapes trying to avoid a repetition of same unit size frequency along a horizontal line (some unit repetition is unavoidable). Avoid stack bonding of unit joints (vertical joint line between adjoining units) for more than two courses vertically.
1) Prepare the base leveling pad.
2) Install the base course.
3) Insert the fiberglass pins.
4) Install backfill and compaction.
5) Install additional courses.
6) Capping the wall.
Click on the images for more detailed information on each step.